BAA Case StudyBAA – Heathrow Terminal 5 Planning

The Scenario

BAA owns and runs 7 UK airports, including Heathrow, the world’s busiest international airport. In order to increase capacity, efficiency and airline-passenger service, BAA commissioned Terminal 5. Terminal 5 was designed for 60 aircraft stands and 30 million passengers per year and would also be linked to two satellite concourse buildings by underground people movers. It would be the largest construction project in Europe, cost £4bn, and open in March 2008. BAA needed to ensure that the new facility would meet capacity and customer service demands.

The Challenge

The design, size and layout of the terminal and the positioning of service points of the airport would be major factors in determining its performance, so decisions had to be made early - and BAA and their customers would have to live with the consequences. Major mistakes could not be contemplated. BAA needed to examine and compare alternative design options and consider the following:

  • How much floor space would be required and how is it best laid out to accommodate passengers on concourses and in lounges?
  • How many service points would be needed to meet target service times?
  • Where should passenger service points and movement systems be located for maximum throughput and minimum delays?
  • Schedules and required flow rates vary hugely during the day. Can the design cope with peaks in demand?
  • How will the process design cope if predicted passenger volumes are under-estimated by 10%, 20%?
  • What will be the impact on concourse and lounge congestion of flight delays?
  • How would new technologies such as biometrics and self-service check-in affect service times?
  • How will the trend to larger aircraft affect service levels both now and in the future?

To help solve these issues, BAA’s Operational Research Team commissioned Paragon Simulation to produce a user-operated configurable model of the new Terminal.

BAA Case StudyThe Solution

The model produced by Paragon was highly visual and animated, so that the proposed size, layout and key facilities of the terminal could be replicated and passengers and their movements could be seen. The model collected statistics on performance, but the animation added another dimension – bottlenecks and congestion that would be unpleasant for passengers as well as problematic for efficiency could be understood, and the impact of design changes could be visualised.

The model could then be run with alternative layouts, and with varying numbers of service points and staff to replicate different operating load conditions. The model calculated the number of service points needed in each hour of every day to account for varying demand.

The Benefits

BAA’s process designers and analysts used the model to compare various scenarios until they were confident that their design offered the best compromises and met key targets efficiently without wasteful redundancy. The results of the modelling greatly influenced the size and layout, and service point numbers and positioning of Terminal 5.

BAA Case StudyBAA also used the results in negotiations to convince airlines that “customer experience” expectations would be met without acceding to demands for unnecessary extra capacity.

The Paragon Information Manager Interface, designed for easy non-expert use, will also allow BAA to test any proposed schedule and operating changes once the terminal is operating to see the impact before implementation. Consequently, it can be used to determine how many service points need to be staffed at times of varying demand, once they have real operating experience.

The model is truly flexible as it can also configured to model other Heathrow terminals (selectable through the Paragon ‘Scenario Manager’) and other BAA airports, and so will be a major planning tool for BAA for many years.

Download this case study as a PDF.

case studies

World Business Council for Sustainable Development

***New*** ...Cement Sustainability Initiative Sectoral Model

A business model used to significantly reduce the carbon produced from the world-wide cement trade...more details>>>

United Utilities

Waste Management & Recycling

United Utilities wins a competitive tender using animated simulation to convince the customer their design will perform....more details>>>

ThyssenKrupp

One of the world's biggest technology groups

A model to support a competitive aerospace industry tender bid. The bid challenged conventional industry practice and offered improved returns through automation and labour reduction....more details>>>

Xerox

Office products, workflow and document management

Major investment in an assembly area for a new breed of printer - needed an animated model of the assembly circuit for Xerox to operate...more details>>>

Ibstock

One of the UK's largest brick manufacturers

A need to plan for maximum throughput in times of high demand (and prices) and greatest resilience to downturns and price erosion....more details>>>

BAA

Terminal 5

A generic simulation tool that showed BAA the impact on passengers of varying aircraft schedules and plane types, future passenger volumes and check-in resources...more details>>>

Sellafield

Fuel manufacture & reprocessing, and waste remediation and decommissioning

A simulation that identified the throughput capability of a waste processing system, and enabled savings in costs in excess of £100m...more details>>>

Tesco

Distribution Centre

Tesco needed an independent assessment of the impact of proposed changes and whether efficiency and loading time targets would be met. The materials handling supplier recommended Paragon Simulation....more details>>>

NHS

Accident & Emergency Facilities

Consolidation of local NHS Accident & Emergency facilities to improve services and reduce the costs compared to the existing multiple smaller facilities....more details>>>

Outokumpu

Worldwide stainless steel manufacture

A generic simulation of stainless steel process enabled them to reduce inventory, increase efficiency, and produce schedules that minimised waste....more details>>>