Find out about modelling
Find out who we are

NHS Consolidation Case Study

nhs logo

The Scenario

A consolidation of local NHS Accident & Emergency facilities in Newcastle-on-Tyne was planned. The objective was to improve services and reduce the costs compared to the existing multiple smaller facilities. Consequently, a new and improved facility was to be built at the Royal Victoria Infirmary.

The Challenge

Management were keen to control costs. Build costs were closely related to floor space (£1200/m2) and management wanted to provide space for 22 separate rooms and argued that these would provide sufficient capacity. Clinicians, mindful of clinical needs and the expansion in treatments required, argued for a much bigger facility with 35 rooms - an argument rejected by management on grounds of cost. With best intentions on both sides, a stand-off resulted. Both sides considered their case justified, but there was no way of impartially reconciling opposing views.

The complexity of the problem and the fact that previously much data was entered onto computer systems but very little real information on performance was available meant that a new approach was required.

The Solution

A model of the facility was commissioned from Paragon Simulation to provide independent analysis. Paragon worked closely with the project team, consisting of key Clinical and Nursing staff and the heads of A&E and Hospital Planning. The first stage was to understand the A&E process in a much more systematic way than had been the case in the past. Paragon’s model showed a configurable plan view of the proposed A&E area facilities, layout and the workflows between various a

reas of the department. Conflicts and bottlenecks could be clearly seen. The model dynamically simulated A&E arrivals (normal and random variations), the time and workforce skills needed for various treatments, workflows, rosters, and complex routing within the facility. Results in terms of throughput, waiting times, waiting numbers and efficiency of resource utilisation and other key indicators could be displayed in graphical and tabular formats. Multiple design scenarios could also be considered and tested quickly and results compared.

The Benefits

The first result was a diplomatic one - all parties involved agreed that the model provided an accurate and unbiased representation of the facility, resource requirements, workflows and outcomes. Consequently, all parties could then work together using an agreed set of ‘rules’ with a common aim. The model revealed that by optimising work flows and the correct size and positioning of rooms and facilities within the A&E department, the performance requirements could be met within the original floor space proposed by managers – therefore keeping within budget. However, it showed that a greater number of smaller rooms - 26 - would be required to meet performance objectives. It also revealed the best ways to organise staff rosters and workflows for maximum efficiency. All parties had confidence - before implementation - that the plan was robust and would cope with all anticipated operating scenarios.

NHS Case Study Graphic 1

NHS Case Study Graphic 2

Download this Case Study as a pdf

case studies

World Business Council for Sustainable Development

***New*** ...Cement Sustainability Initiative Sectoral Model

A business model used to significantly reduce the carbon produced from the world-wide cement trade...more details>>>

United Utilities

Waste Management & Recycling

United Utilities wins a competitive tender using animated simulation to convince the customer their design will perform....more details>>>

ThyssenKrupp

One of the world's biggest technology groups

A model to support a competitive aerospace industry tender bid. The bid challenged conventional industry practice and offered improved returns through automation and labour reduction....more details>>>

Xerox

Office products, workflow and document management

Major investment in an assembly area for a new breed of printer - needed an animated model of the assembly circuit for Xerox to operate...more details>>>

Ibstock

One of the UK's largest brick manufacturers

A need to plan for maximum throughput in times of high demand (and prices) and greatest resilience to downturns and price erosion....more details>>>

BAA

Terminal 5

A generic simulation tool that showed BAA the impact on passengers of varying aircraft schedules and plane types, future passenger volumes and check-in resources...more details>>>

Sellafield

Fuel manufacture & reprocessing, and waste remediation and decommissioning

A simulation that identified the throughput capability of a waste processing system, and enabled savings in costs in excess of £100m...more details>>>

Tesco

Distribution Centre

Tesco needed an independent assessment of the impact of proposed changes and whether efficiency and loading time targets would be met. The materials handling supplier recommended Paragon Simulation....more details>>>

NHS

Accident & Emergency Facilities

Consolidation of local NHS Accident & Emergency facilities to improve services and reduce the costs compared to the existing multiple smaller facilities....more details>>>

Outokumpu

Worldwide stainless steel manufacture

A generic simulation of stainless steel process enabled them to reduce inventory, increase efficiency, and produce schedules that minimised waste....more details>>>